Share on LinkedInShare on LinkedIn

ARTICLE · 31 MARCH 2020

The End Of The Long And Winding Road? The Federal Court Of Appeal Upholds The Trans Mountain Pipeline Expansion Project

Willms & Shier Environmental Lawyers LLP
Explore more from Willms & Shier Environmental Lawyers LLP

On February 7, 2020, the Federal Court of Appeal (the "FCA") upheld the approval of the proposed Trans Mountain Pipeline Expansion Project (the "Project") in its decision in...

CanadaEnvironment

On February 7, 2020, the Federal Court of Appeal (the "FCA") upheld the approval of the proposed Trans Mountain Pipeline Expansion Project (the "Project") in its decision in Coldwater First Nation v Canada (Attorney General). 1 The FCA's decision follows the FCA's previous decision in Tsleil-Waututh Nation v Canada (Attorney General), 2 ("Tsleil-Waututh Nation") in which the FCA quashed the approval of the Project and remitted the matter back to the Governor in Council for redetermination.

History of Project Approvals

On November 29, 2016, the Governor in Council approved the Project following the National Energy's Board's ("Board") recommendation to approve the Project.

In Tsleil-Waututh Nation, several applicants successfully challenged the Governor in Council's decision. The FCA found two fundamental defects: failure to assess the impact on endangered Southern Resident Killer Whales and the Crown's failure to adequately fulfil its duty to consult with

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from