Share on LinkedInShare on LinkedIn

ARTICLE · 25 JUNE 2024

Shutting The Open Door: B.C. Court Of Appeal Overturns Contractor's Claim For Cost Recovery Under The EMA

McMillan LLP
McMillan LLP
Contributor
McMillan LLP

McMillan LLP

The firm : McMillan LLP is one of Canada’s leading national law firms with offices in Montreal,...

View firm profile
Explore more from McMillan LLP

Nearly a year ago, the Supreme Court of British Columbia opened the door for contractors to pursue former owners and operators of contaminated sites to recover unpaid fees for remediation work performed by the contractor.

CanadaEnvironment

Nearly a year ago, the Supreme Court of British Columbia opened the door for contractors to pursue former owners and operators of contaminated sites to recover unpaid fees for remediation work performed by the contractor. 1 The door was opened by the contractor's novel argument that it could seek recourse under the cost-recovery provisions of the province's Environmental Management Act (the "EMA") in circumstances where the contractor had not been paid by the party it contracted with to perform the remediation work.

On June 19, 2024, the British Columbia Court of Appeal rejected the contractor's argument and overturned the lower court's decision that the EMA's cost recovery provisions could apply to debt claims for contracted remediation services performed by unpaid contractors,2 With the Court of Appeal's recent decision, there is now clearer guidance on the cost recovery provisions of the EMA and confirmation of the primary purpose of the legislation to: (1)

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The foregoing provides only an overview and does not constitute legal advice. Readers are cautioned against making any decisions based on this material alone. Rather, specific legal advice should be obtained.

© McMillan LLP 2025

See more popular content from