Case citation: Paramount Resources Ltd v Grey Owl Engineering
Ltd, 2024 ABCA 60
When the polluter pays for the clean-up costs of a pipeline
leak, can they then turn around and seek to recover these costs
from the parties responsible for installing the pipeline decades
before? That was the issue facing the Alberta Court of Appeal in
Paramount Resources Ltd v Grey Owl Engineering Ltd, 2024
ABCA 60. For only the second time, the Court of Appeal considered
s. 218 of the Environmental Protection and Enhancement Act
and whether limitation periods should be extended in the context of
environmental pollution claims.
In, Paramount, Brownlee LLP (along with co-defence
counsel) successfully argued that the Plaintiff's limitation
period should not be extended to permit a $20 million-dollar
environmental claim to proceed against the parties who were
involved in the transition of a steel pipeline into a fiberglass
one over 10 years before the leak occurred.