Federal Court Of Appeal Overturns Lower Court's Revocation Of Darlington Nuclear Project Licence – Nuclear Project Allowed To Proceed

On September 10, 2015, the Federal Court of Appeal (FCA) overturned the decision of the Federal Court of Canada (FCC) in Greenpeace Canada v. Attorney General of Canada, 2014 FC 463.

CanadaEnvironment

On September 10, 2015, the Federal Court of Appeal (FCA) overturned the decision of the Federal Court of Canada (FCC) in Greenpeace Canada v. Attorney General of Canada, 2014 FC 463, which had (i) revoked the Site Preparation Licence (Licence) issued to Ontario Power Generation (OPG) to construct new nuclear generation units at the existing Darlington nuclear facility, and (ii) ordered that the environmental assessment (EA) under the Canadian Environmental Assessment Act (CEAA 1992)1 be returned to the Joint Review Panel (JRP) for further consideration.

This decision affirms the existing understanding of the role of a JRP tasked with gathering and "considering" the potential environmental effects of a project under sections 16(1)(a) and (b) of CEAA 1992. The FCA applied the well-established standard that the JRP must give "some consideration" to the relevant issues; since the CEAA 1992 does not stipulate how an environmental effect is to be considered, the scope

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from