On April 20, 2015, the Ontario Court of Appeal released its
decision restoring the ERT's conclusion that a nine turbine
wind energy project at Ostrander Point near Picton, Ontario would
cause serious and irreversible harm to the Blanding's turtle.
The Court sent the matter back to the ERT to hear further
submissions and determine the appropriate remedy.
As we have reported previously (click
here), in July 2013, the ERT revoked the renewable energy
approval issued by the Ontario Ministry of the Environment and
Climate Change (MOECC) to Ostrander Point GP (Ostrander) on the
grounds that the project would cause serious and irreversible harm
to a population of Blanding's turtles, a threatened species in
Ontario. The ERT concluded that traffic on 5.4 km of access roads
to the project, together with an increase in poaching and
predators, would cause this sort of harm to the turtles located on
the project site and surrounding area. As a result, the ERT revoked
the approval