B.C. Court Of Appeal Review Of The BC Environmental Assessment Process – Case Comment On Fort Nelson First Nation v. British Columbia

In Fort Nelson First Nation v. British Columbia (Environmental Assessment Office), 2016 BCCA 500, the B.C. Court of Appeal recently considered three issues involving the Reviewable Projects Regulation under B.C.'s Environmental Assessment Act:

CanadaEnvironment

Introduction

In Fort Nelson First Nation v. British Columbia (Environmental Assessment Office), 2016 BCCA 500, the B.C. Court of Appeal recently considered three issues involving the Reviewable Projects Regulation under B.C.'s Environmental Assessment Act:

  1. whether a letter from the Environmental Assessment Office ("EAO") confirming a proponent's interpretation of the Regulation is a judicially reviewable "decision";
  2. the interpretation of the threshold to trigger a provincial environmental assessment of a proposed sand and gravel pit; and
  3. whether the EAO's communication to the proponent could amount to "Crown conduct" that triggers a Crown duty to consult with potentially affected Aboriginal peoples.