On August 30, 2018, the Federal Court of Appeal (the
Court) released its decision1 on the
federal government's approval of the Trans Mountain Expansion
Project (TMX). The Court quashed the approval on
two grounds:
- The National Energy Board
(NEB or Board) unjustifiably
defined the scope of the project not to include project-related
tanker traffic, such that the government could not rely on the
NEB's report; and
- The federal government's
consultation with Indigenous peoples after the NEB issued its
report, but before it made its decision to approve the project, was
inadequate.
In this post, we will discuss the first of these reasons for the
Court quashing the approval (exclusion of marine shipping). We will
discuss the second reason (inadequate Indigenous consultation) in a
subsequent post.