A Triumph Of Form Over Substance? The Federal Court Of Appeal's Decision To Quash The Trans Mountain Expansion Approval

On August 30, 2018, the Federal Court of Appeal (the Court) released its decision on the federal government's approval of the Trans Mountain Expansion Project (TMX).

CanadaEnvironment

On August 30, 2018, the Federal Court of Appeal (the Court) released its decision1 on the federal government's approval of the Trans Mountain Expansion Project (TMX). The Court quashed the approval on two grounds:

  1. The National Energy Board (NEB or Board) unjustifiably defined the scope of the project not to include project-related tanker traffic, such that the government could not rely on the NEB's report; and  
  2. The federal government's consultation with Indigenous peoples after the NEB issued its report, but before it made its decision to approve the project, was inadequate.

In this post, we will discuss the first of these reasons for the Court quashing the approval (exclusion of marine shipping). We will discuss the second reason (inadequate Indigenous consultation) in a subsequent post.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from