Regulated Utilities Have An Opportunity, But Not A Right, To Recover Costs

Alberta’s Court of Appeal affirmed the Alberta Utilities Commission’s ability to limit the recovery of legal costs in non-rate-setting proceedings.

CanadaEnergy and Natural Resources

Alberta's Court of Appeal affirmed the Alberta Utilities Commission's ability to limit the recovery of legal costs in non-rate-setting proceedings.

Background

ATCO Gas and Pipelines Ltd. and ATCO Electric Ltd. (ATCO Utilities) had participated in two proceedings before the Alberta Utilities Commission. The first proceeding was a Utility Asset Disposition Proceeding (UAD Proceeding) in which the commission invited industry participants to make submissions on the ramifications of the Supreme Court's decision in Stores Block.

Stores Block had changed the regulatory landscape, as it effectively upended what had been long-standing rate-making practice insofar as it allowed utility shareholders to take the full benefit of an appreciated asset (land) even though the asset had originally formed part of the rate base on which rates had been calculated and paid by ratepayers. The commission held that ATCO Utilities was not entitled to recover its legal costs for the initial stages of the UAD