On May 15, 2017, the FCA issued its reasons for an order in Tsleil-Waututh Nation et al v Attorney General of Canada, National Energy Board, and Trans Mountain Pipeline, 2017 FCA 104...

CanadaEnergy and Natural Resources

On May 15, 2017, the Federal Court of Appeal (FCA) issued its reasons for an order in Tsleil-Waututh Nation et al v Attorney General of Canada, National Energy Board, and Trans Mountain Pipeline, 2017 FCA 104, granting the Attorney General of Alberta (AGA) leave to intervene in the proceedings. The judicial review challenges a National Energy Board (NEB) report and recommendation, as well as a Governor in Council's order approving the expansion of the Trans Mountain Pipeline.

Background

On May 19, 2016, the NEB issued a report which found Kinder Morgan's proposed Trans Mountain Expansion Project (Project) to be in Canada's public interest, and recommended that the federal Governor in Council conditionally approve the Project. The Project – at a purported cost of $7.4 billion – will expand the existing marine terminal in Burnaby, BC, add approximately 987 km of new pipeline with new and modified facilities, and increase capacity from 300,000 barrels per day