The cost of electricity for Ontario consumers has increased substantially over the last decade.

CanadaEnergy and Natural Resources

In our August 2016 Blakes Bulletin: September Deadline: Last Chance to Participate in Ontario's Large Renewable Procurement Program, we reported that Ontario was moving ahead with the Request for Qualifications (RFQ) portion of phase two of the province's Large Renewable Procurement program (LRP). However, in a surprising move, on September 27, 2016, Ontario announced that it is suspending all new procurements of renewable generation capacity under the LRP and cancelling the RFQ process.

The LRP was a competitive process for procuring renewable electricity projects; it was instituted in 2014 as a replacement to the large renewable portion of Ontario's previous feed-in tariff program. The first phase of the LRP was concluded in April 2016 with Ontario awarding contracts for the development of 16 renewable generation projects. Prior to the September 27, 2016 announcement, it was expected that Ontario would be awarding several other contracts for additional renewable