Ontario Approves Construction Of First-of-its-kind Small Modular Reactor

Borden Ladner Gervais LLP
Borden Ladner Gervais LLP
Contributor
Borden Ladner Gervais LLP

Borden Ladner Gervais LLP

With over 750 lawyers, intellectual property agents and other professionals, BLG services...

View firm profile
Explore more from Borden Ladner Gervais LLP

On May 8, 2025, the Province of Ontario announced that it approved Ontario Power Generation's (OPG) plan to begin construction on the first of four small modular reactors (SMR) at the Darlington nuclear site.

CanadaEnergy and Natural Resources

On May 8, 2025, the Province of Ontario announced that it approved Ontario Power Generation's (OPG) plan to begin construction on the first of four small modular reactors (SMR) at the Darlington nuclear site.

The four SMRs are referred to collectively as the Darlington New Nuclear Project, or DNNP. OPG's budget for the DNNP, which includes site preparation, engineering and design work to date, as well as the construction of all four SMRs, is set at C$20.9 billion (US$15.2 billion). The Province's approval of construction of the DNNP follows the issuance of a decision of the Canadian Nuclear Safety Commission (the Commission) on April 4, 2025, which issued Canada's first regulatory approval to construct the first SMR of the DNNP.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from