One Step Forward In The LRP Process: Qualified Applicants List Has Been Released

In June 2012, the Ontario Minister of Energy directed the Ontario Power Authority to begin development of what is now known as the Large Renewable Procurement.

CanadaEnergy and Natural Resources

Large Renewal Procurement

In June 2012, the Ontario Minister of Energy directed the Ontario Power Authority (the "OPA") to begin development of what is now known as the Large Renewable Procurement (the "LRP"). The LRP is a competitive process for the procurement of large renewable energy projects generally greater than 500 kW. The procurement targets are as follows:

Wind Solar Bioenergy Hydro
2015 300 MW 140 MW 50 MW 50 MW
2016 300 MW 140 MW 50 MW 45 MW

The OPA's final recommendations report, prepared for the Minister of Energy, was released in February 2014. The report included proposed elements of subsequent stages of the procurement process including the request for qualifications and request for proposals.