ARTICLE · 09 APRIL 2019

Nova Scotia Revokes Licence For Cape Sharp Tidal And Orders Removal Of Turbine

Aird & Berlis LLP
Aird & Berlis LLP
Contributor
Aird & Berlis LLP

Aird & Berlis LLP

Aird & Berlis is a leading Canadian law firm, serving clients across Canada and globally. With...

View firm profile
Explore more from Aird & Berlis LLP

On April 3, 2019, the Nova Scotia Department of Energy and Mines announced that it has revoked the marine renewable-electricity licence issued to Cape Sharp Tidal Venture Ltd.

CanadaEnergy and Natural Resources

On April 3, 2019, the Nova Scotia Department of Energy and Mines announced that it has revoked the marine renewable-electricity licence issued to Cape Sharp Tidal Venture Ltd. This means that the company is no longer permitted to operate the tidal energy project and must retrieve its turbine in the Midas Basin of the Bay of Fundy. If the turbine is not removed in a reasonable timeframe, the government may seize the security that the company posted.

As discussed in previous posts (here and here), Cape Sharp Tidal has been a joint venture between Ireland-based OpenHydro and Nova Scotia Power affiliate Emera, created to deploy two 2MW tidal turbines in Minas Passage at the Fundy Ocean Research Centre for Energy (FORCE) test site. The project was intended to test the viability of new in-stream tidal energy technology. Nova Scotia issued the marine renewable-electricity licence to Cape Sharp Tidal in May 2018, permitting the company to (among other things) construct

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.