New Schedule Issued For The Energy East Pipeline Project Review Processes

There have been several recent developments in the approval and review process for TransCanada's Energy East pipeline project.

CanadaEnergy and Natural Resources

There have been several recent developments in the approval and review process for TransCanada's Energy East pipeline project.

Most significantly, on April 26, 2016, the National Energy Board (NEB) issued a "preliminary timeline" for the hearing process, which indicates that the NEB's report on the project will be issued by March 2018. The timeframe for the NEB's process has been extended to 21 months for the process versus the usual 15 month time limit. That is in keeping with the Federal Government's January 27, 2016 announcement that the time for NEB review of the Energy East project would be extended by six months (see our previous post discussing changes to the interim approach that the Government will require for the review of major projects currently under environmental review). The NEB's report on the project will be presented the Federal Cabinet, who will then have six months to make a decision.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from