On February 22, 2019, the National Energy Board ("NEB" or the "Board") released its reconsideration report (the "Reconsideration") on the Trans Mountain Expansion Project (the "Project").

CanadaEnergy and Natural Resources

Introduction

On February 22, 2019, the National Energy Board ("NEB" or the "Board") released its reconsideration report (the "Reconsideration") on the Trans Mountain Expansion Project (the "Project"). The Reconsideration follows the August 2018 Federal Court of Appeal decision that set aside the NEB's previous approval of the Project and the federal government's subsequent direction for the NEB to reconsider the Project to take into account Project-related marine shipping. In its lengthy report, the Board recommends the approval of the Project subject to the 156 conditions that it had proposed in its previous recommendation and 16 new recommendations that are aimed at mitigating the environmental impacts of marine shipping that are beyond the scope of the Board's regulatory authority. This recommendation flows from the Board's finding that the Project is in the Canadian public interest and is required by present and future public convenience and necessity. The

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

Please add at the end of every article before the disclaimer (remember to change the article id):

About BLG

See more popular content from