On January 9, 2020, the B.C. Supreme Court in Walton v. Warren 2020 BCSC 19 found in favour of the Purchaser when an undiscovered underground storage tank required removal ...

CanadaEnergy and Natural Resources

On January 9, 2020, the B.C. Supreme Court in Walton v. Warren 2020 BCSC 19 found in favour of the Purchaser when an undiscovered underground storage tank required removal and site remediation following closing. This ruling was given despite the Purchaser having signed off on an inspection report prior to closing. The purchase and sale agreement provided that the Seller had to ensure that any underground storage tank (UST) located on the property be removed and the surrounding soil remediated. The Seller was responsible for all costs. The Seller had to provide written confirmation before the Completion Date from the tank removal contractor and relevant provincial and local authorities that the remediation complied with provincial or local government laws. The Purchaser had to obtain and approve an inspection report 6 weeks before the completion date. The report recommended that a specialist company survey and sweep the property to determine the presence of buried oil

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from