FERC Rejects Secretary Of Energy Direction To Assure Cost Recovery For Coal And Nuclear Generators

Aird & Berlis LLP
Aird & Berlis LLP
Contributor
Aird & Berlis LLP

Aird & Berlis LLP

Aird & Berlis is a leading Canadian law firm, serving clients across Canada and globally. With...

View firm profile
Explore more from Aird & Berlis LLP

On January 8, 2018, the Federal Energy Regulatory Commission (FERC) issued an Order terminating a rulemaking proceeding ordered by the U.S. Secretary of Energy (Rick Perry).

CanadaEnergy and Natural Resources

On January 8, 2018, the Federal Energy Regulatory Commission (FERC) issued an Order terminating a rulemaking proceeding ordered by the U.S. Secretary of Energy (Rick Perry). This overrules Secretary Perry's September 2017 Direction and "Notice of Proposed Rulemaking" to the FERC requiring the establishment of market rules to assure cost recovery for baseload generators.

As discussed in an earlier post, the specific requirement was for FERC to enact rules that allow for "the recovery of costs of fuel-secure generation units that make [the] grid reliable and resilient." The Direction is premised on a stated concern that the American public needs protection from "the threat of energy outages that could result from the loss of traditional baseload capacity." The requirement would apply to generation units that can provide essential energy and ancillary reliability services and have a 90-day fuel supply on site in the event of supply disruptions caused by emergencies and