Share on LinkedInShare on LinkedIn

ARTICLE · 14 JULY 2016

Federal Court Of Appeal Quashes Northern Gateway Pipeline Certificates For Failure To Consult Aboriginal Peoples

Aird & Berlis LLP
Aird & Berlis LLP
Contributor
Aird & Berlis LLP

Aird & Berlis LLP

Aird & Berlis is a leading Canadian law firm, serving clients across Canada and globally. With...

View firm profile
Explore more from Aird & Berlis LLP

The Federal Court of Appeal quashed two Certificates of Public Convenience and Necessity issued for the Enbridge Northern Gateway Pipeline in a 2-1 decision delivered on June 23, 2016.

CanadaEnergy and Natural Resources

The Federal Court of Appeal quashed two Certificates of Public Convenience and Necessity issued for the Enbridge Northern Gateway Pipeline in a 2-1 decision delivered on June 23, 2016. The Certificates are required under the National Energy Board Act for Northern Gateway to begin construction of the pipeline.

The proposed pipeline would run approximately 1,177 km delivering an average of 525,000 barrels of oil per day from Bruderheim, Alberta across northern British Columbia to the deep-water port of Kitimat. The National Energy Board (NEB) originally issued Certificates approving the pipeline project in June 2014 following the decision of the Governor in Council. However, several coastal First Nations groups and non-profit environmental organizations promptly brought applications challenging the decision.