Share on LinkedInShare on LinkedIn

ARTICLE · 10 NOVEMBER 2017

British Columbia Utilities Commission Issues Final Report About Site C Project

On November 1, 2017, the British Columbia Utilities Commission (BCUC) issued its Final Report on BC Hydro's "Site C" hydroelectric project.

CanadaEnergy and Natural Resources

On November 1, 2017, the British Columbia Utilities Commission (BCUC) issued its Final Report on BC Hydro's "Site C" hydroelectric project. This Final Report represents the culmination of a nearly three-month long investigatory and consultative process to re-examine the viability and appropriateness of the partially-completed $8.3 billion facility. The Final Report makes no recommendation about whether the project should proceed, but warns that that the costs of the project (if completed) will be higher than expected. The Final Report indicates that the benefits (generation) from the Site C project could be obtained through other renewable generation projects at lower costs, but notes that there will be costs associated with terminating or suspending the Site C project.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from