The National Energy Board (NEB) has determined that the Coastal
GasLink Pipeline Project (CGLP) does not fall within its
jurisdiction. The CGLP is a proposed 670 km natural gas pipeline
entirely within the province of British Columbia that would supply
the LNG Canada Project. The CGLP was authorized
by, and is currently regulated by, the British Columbia Oil and Gas
Commission. As discussed in an earlier post, an NEB proceeding was
prompted by an application by Michael Sawyer in July 2018, who
argued that the CGLP, along with the existing NOVA Gas Transmission
Ltd. (NGTL) System, comprise of a single federal undertaking and is
therefore subject to federal regulation under the NEB.
In his application, Mr. Sawyer referred to the Federal Court of
Appeal's
decision regarding the NEB's jurisdiction over the proposed
Prince Rupert Gas Transmission Project (PRGTP). In that decision, the FCA found that
there was a prima facie case that the PRGTP appeared to be
functionally