On January 20, 2015, the Alberta Utilities Commission released Decision 790-D02-2015, Milner Power Inc. and ATCO Power Ltd. Re: Complaints.

CanadaEnergy and Natural Resources

On January 20, 2015, the Alberta Utilities Commission ("AUC" or the "Commission") released Decision 790-D02-2015, Milner Power Inc. and ATCO Power Ltd. Re: Complaints regarding the ISO Transmission Loss Factor Rule and Loss Factor Methodology, Phase 2 Module A, which can be accessed here (click here for decision).

In previous decisions, AUC 2012-104 (found here) and AUC 2014-110 (found here), the AUC determined and confirmed that the Independent System Operator ("ISO")'s Line Loss Rule was unjust, unreasonable, unduly preferential, arbitrarily and unjustly discriminatory on the basis that the rule disadvantaged generators that are loss savers and does not properly charge loss creators for their losses.  The AUC determined in those decisions that the Line Loss Rule was ultimately inconsistent with the Electric Utilities Act ("EUA") and the Transmission Regulation made thereunder.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.