All Shook Up: New Amendments To B.C.'s Drilling And Production Regulation Requiring Seismic Event Reporting

Borden Ladner Gervais LLP
Borden Ladner Gervais LLP
Contributor
Borden Ladner Gervais LLP

Borden Ladner Gervais LLP

With over 750 lawyers, intellectual property agents and other professionals, BLG services...

View firm profile
Explore more from Borden Ladner Gervais LLP

The fact that the permit holder must report any seismic activity where a person feels ground motion is significant, given that a feeling of ground motion is highly subjective.

CanadaEnergy and Natural Resources

On August 6, 2015, the B.C. Oil and Gas Commission (the "OGC") announced that it had approved amendments to the Drilling and Production Regulation that would, among other things, regulate the reporting requirements of permit holders relating to seismic events.

Previously, the regulations did not require permit holders to report seismic events. However, some permit holders were required to report seismic activity as a term of their permit, particularly those involved in fracturing and disposal activities in the Horn River Basin.

In December 2014, the OGC released its Investigation of Observed Seismicity in the Montney Trend report (the "Seismicity Report"), which concluded that fluid injection during fracturing operations in the Montney Trend had caused low-level seismic activity. The Seismicity Report also linked waste water disposal in the area to seismic activity. These findings caused the OGC to conclude that induced seismic activity was not limited to the Horn