ARTICLE · 06 MARCH 2017

Alberta Utilities Commission Rules On The Scope Of Evidence Required By First Nations And Métis On Notice Of Constitutional Question And The AUC's Jurisdiction To Assess Crown Consultation

Borden Ladner Gervais LLP
Borden Ladner Gervais LLP
Contributor
Borden Ladner Gervais LLP

Borden Ladner Gervais LLP

With over 750 lawyers, intellectual property agents and other professionals, BLG services...

View firm profile
Explore more from Borden Ladner Gervais LLP

In Fort McMurray West 500-kV Transmission Project (Proceeding 21030) Ruling on jurisdiction to determine the questions stated in the Notices of Questions of Constitutional Law...

CanadaEnergy and Natural Resources

In our  previous blog we analyzed two judicial review decisions of the Alberta Court of Queen's Bench defining the scope of procedural fairness and the information requirements in assessing whether the Alberta Crown's duty to consult has been triggered in resource development applications before the Alberta Energy Regulator (AER).  In Fort McMurray West 500-kV Transmission Project (Proceeding 21030) Ruling on jurisdiction to determine the questions stated in the Notices of Questions of Constitutional Law (October 7, 2016) (the Letter Decision), the Alberta Utilities Commission (AUC) determined the scope of information required on Notices of Questions of Constitutional Law (NQCLs) submitted by First Nations and Métis groups relating to their asserted or established rights, as well as the AUC's jurisdiction to assess the adequacy of Crown consultation as requested in the NQCLs. 