ARTICLE · 18 NOVEMBER 2014

A Mountain Of A Battle: BC Supreme Court Grants An Injunction Restraining Protestors From Interfering With Trans Mountain’s Pipeline Expansion Project

Borden Ladner Gervais LLP
Borden Ladner Gervais LLP
Contributor
Borden Ladner Gervais LLP

Borden Ladner Gervais LLP

With over 750 lawyers, intellectual property agents and other professionals, BLG services...

View firm profile
Explore more from Borden Ladner Gervais LLP

The latest episode in the ongoing and expanding saga of pipeline opposition in British Columbia is the BC Supreme Court’s decision on November 14, 2014 granting an injunction to Trans Mountain Pipeline ULC.

CanadaEnergy and Natural Resources

The latest episode in the ongoing and expanding saga of pipeline opposition in British Columbia is the BC Supreme Court's decision on November 14, 2014 granting an injunction to Trans Mountain Pipeline ULC ("Trans Mountain") to prevent protestors from continuing to interfere with Trans Mountain's investigative work in the City of Burnaby. The work is part of Trans Mountain's investigation of routing options for its proposed pipeline expansion from Edmonton to Burnaby. A full copy of the decision can be found here.

Trans Mountain sought an injunction to stop protesters from interfering with the survey and drilling work for the assessments required by the National Energy Board ("NEB"). The geotechnical work will include borehole testing within a conservation area on Burnaby Mountain, which is required to determine the feasibility of a tunnel under Burnaby Mountain. The work has been prevented to date by protestors who used aggressive and threatening tactics to disrupt