Some certainty in post completion liability
You get what you pay for. A builder prices its works based on
risk, including risk of future liability to successors in title to
a property.
So why did it take a High Court decision to find that a
builder's liability is usually limited by its contract with a
developer?
In a unanimous decision delivered on 8 October 2014 the High
Court overturned a decision of the New South Wales Court of Appeal
which had otherwise caused considerable concern for builders and
developers with respect to their liability in negligence for latent
defects. All 7 judges heard the appeal and agreed that it should be
allowed.
This landmark decision will provide considerable comfort for the
industry. Whilst not a panacea for the morass that surrounds
liability for pure economic loss, the judgment further provides at
least some clarity in this vexed area of law.