When near enough just is not good enough – the return of security prior to completion

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

Recent case highlights issues around security rights that need to be considered when negotiating a contract.

AustraliaReal Estate and Construction

The return of security held under construction contracts signifies the works reaching practical completion and then, finally, the end of the contractual relationship.

A party's right to the return of its security is often prescribed by the contract. But what happens to the security if the contract is terminated or the works are taken out of the contractor's hands prior to the works reaching completion? A contract is more often than not completely silent as to what happens.

The recent case of Galileo Miranda Nominee Pty Ltd v Duffy Kennedy Pty Ltd [2019] NSWSC 1157, considered these issues and identified a number of questions that both principals and contractors should consider at the time of negotiating the contract when it comes down to security rights.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This publication does not deal with every important topic or change in law and is not intended to be relied upon as a substitute for legal or other advice that may be relevant to the reader's specific circumstances. If you have found this publication of interest and would like to know more or wish to obtain legal advice relevant to your circumstances please contact one of the named individuals listed.

See more popular content from