ARTICLE · 04 OCTOBER 2023

Residential Focus: Jurisdiction (revisited) and transfer

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

The Tribunal's jurisdiction under section 48K of the Home Building Act 1989 (NSW) (HBA) is full of curiosities.

AustraliaReal Estate and Construction

The Tribunal's jurisdiction under section 48K of the Home Building Act 1989 (NSW) (HBA) is full of curiosities. For example, although many causes of action for building claims have a limitation period of six years, they can only be brought in the Tribunal (as opposed to elsewhere) within three years of the supply.

It has long been a source of confusion as to whether these shorter limitation periods operate as a constraint on statutory warranty claims and how the various periods interact.

The issue was revisited in Promina Design & Construction v the Owners Strata Plan No 97449 [2023] NSWCATAP 252, where the Appeal Panel considered it in the context of determining whether the Tribunal had the power to transfer proceedings to the District Court. The Appeal Panel considered whether section 48K of the HBA, specifically subsections (3) and (7), deprived the Tribunal of jurisdiction to make an order to transfer the proceedings.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This publication does not deal with every important topic or change in law and is not intended to be relied upon as a substitute for legal or other advice that may be relevant to the reader's specific circumstances. If you have found this publication of interest and would like to know more or wish to obtain legal advice relevant to your circumstances please contact one of the named individuals listed.