We discuss BGC Contracting Pty Ltd v Citygate Properties Pty Ltd [2016] WASC 88.

AustraliaReal Estate and Construction

KEYWORDS: ADJUDICATION; TIME FOR DETERMINATION

KEY TAKEAWAYS

In the recent decision of BGC Contracting Pty Ltd v Citygate Properties Pty Ltd [2016] WASC 88, the Supreme Court of Western Australia quashed two adjudication determinations made by the same adjudicator under the Construction Contracts Act (WA) 2004 (Act).

The first determination was quashed because the adjudicator had not determined the application within time.

The second determination was quashed on the basis of jurisdictional error.

At the heart of the Court's decision with respect to the second determination was a finding that the adjudicator's reasons did not demonstrate a rational approach to determining the relevant payment dispute.