Significant changes to the legislative regime regulating off-the-plan contracts will commence on 1 December 2019.

AustraliaReal Estate and Construction

Significant changes to the legislative regime regulating off-the-plan contracts will commence on 1 December 2019.

These changes will limit the flexibility of a developer to change or adjust key elements in the development over the life of the project, such as the title and governance structure, the timing of when facilities become available and limitations on how the lot can be used.

Developers may now need to dedicate more time and resources at the beginning of a project in order to improve the accuracy of the contract disclosures and reduce the likelihood that material changes to key elements of the project will be required.

Background to the changes

The core of the legislative regime regulating the sale of property in NSW is found in the Conveyancing Act 1919 (NSW) (Conveyancing Act) and the Conveyancing (Sale of Land) Regulations 2017 (NSW) (Regulations).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This publication does not deal with every important topic or change in law and is not intended to be relied upon as a substitute for legal or other advice that may be relevant to the reader's specific circumstances. If you have found this publication of interest and would like to know more or wish to obtain legal advice relevant to your circumstances please contact one of the named individuals listed.

See more popular content from