ARTICLE · 16 MAY 2014

Court says 'game over' on incomplete adjudication application

When serving a document, follow the rules on service (either under the contract or statute) or it could be 'game over'.

AustraliaReal Estate and Construction

IN BRIEF

This article looks at the recent case of Conveyor & General Engineering v Basetec Services with regards to service of documents. In this case, the court gave a timely reminder that when serving a document you must follow the rules on service (either under the contract or under statute) otherwise it could be 'game over'.

Most modern day construction contracts have terms regarding service of documents including the form, substance and timeframe for their submission. In circumstances where the contract is silent on service of documents, certain statutory provisions can provide assistance, depending on the type and nature of the document.

THE FACTS

CGE entered into contracts with Basetec for the supply of pipe rack units for a number of water treatment facilities at Condabri and Reedy Creek. On 30 July 2013, Basetec delivered payment claims for each project under s 17 of the Building and Construction Industry Payments Act 2004 (Qld) ("BCIPA"). On 12