ARTICLE · 15 DECEMBER 2013

Beware the ticking adjudication clock - At least for the moment...

Corrs Chambers Westgarth
Corrs Chambers Westgarth
Contributor
Corrs Chambers Westgarth

Corrs Chambers Westgarth

Corrs Chambers Westgarth is Australia’s leading independent law firm. We provide exceptional legal...

View firm profile
Explore more from Corrs Chambers Westgarth

The recent tribunal decision clarified how the period in s26(1) of the Construction Contracts Act 2004 (WA) is computed.

AustraliaLitigation, Mediation & Arbitration

The recent Western Australian State Administrative Tribunal (the Tribunal) decision in The MCIC Nominees Trust trading as Capital Projects & Developments and Red Ink Homes Pty Ltd [2013] WASAT 177 has clarified how the period in s 26(1) of the Construction Contracts Act 2004 (WA) (Act) is to be computed.

SUMMARY

In short the time that a party has in order to make an adjudication application under s 26 of the Act commences from the moment that the dispute arises and thus the 28 day period referred to in s 26(1) of the Act includes the day on which the payment dispute arose.

BACKGROUND

The Tribunal (constituted by Member Owen-Conway) was asked to review an adjudicator's decision to dismiss an adjudication application made by the MCIC Nominees Trust, trading as Capital Projects & Developments (MCIC) against Red Ink Homes Pty Ltd (Red Ink) without making a finding on the merits.