A cautionary tale from the Technology and Construction List

Recent case highlights the risks of mismanaged litigation - indecision, inconsistent forensic strategy & delayed communication.

AustraliaLitigation, Mediation & Arbitration

Case management is critical in civil litigation. Section 56 of the Civil Procedure Act 2005 (NSW)mandates that the overriding purpose of the rules is to facilitate the just, quick and cheap resolution of the real issues in dispute. The decision of Stevenson J in The Owners – Strata Plan No 95242 v Karimbla Properties (No 42) Pty Ltd [2024] NSWSC 1625 is a timely reminder of the consequences of mismanaged litigation. It highlights the risks of indecision, inconsistent forensic strategy, and delayed communication — particularly where expert evidence forms the backbone of a plaintiff's case.

Background

The plaintiff, the owners corporation of a large residential development in Zetland known as "Symphony", commenced proceedings on 21 April 2023 alleging building defects across the 223-lot scheme. The claim was brought against the developer, builder, and subcontractors (all part of the Meriton Group) in the Supreme Court of New South Wales. The proceedings related to

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from