As always, a flurry of decisions have recently emerged from the Land and Environment Court regarding claims for compensation under the provisions of the Land Acquisition (Just Terms Compensation) Act 1991 (JTC Act). We provide the following updates on a couple of those decisions.

Reinstatement costs and Section 56(3)

The Trustee for Whitcurt Unit Trust v Transport for NSW [2021] NSWLEC 82

This decision offers helpful insights into how the Court is likely to approach claims for reinstatement.

The Applicant, Whitcurt, conducted a golf driving range business on land owned by the Inner West Council. In March 2020, the land was acquired by Transport for NSW.

The Applicant sought compensation for the compulsory acquisition of its leasehold interest in the land under section 66 of the JTC Act. The claim rested on three bases:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from