Buzzacott v Minister for Sustainability, Environment, Water, Population and Communities [2013] FCAFC 111

Corrs Chambers Westgarth
Corrs Chambers Westgarth
Contributor
Corrs Chambers Westgarth

Corrs Chambers Westgarth

Corrs Chambers Westgarth is Australia’s leading independent law firm. We provide exceptional legal...

View firm profile
Explore more from Corrs Chambers Westgarth

As Condition 71 could be severed from the approval, an invalid EPBC Act condition did not bring down the whole approval.

AustraliaEnvironment

An invalid EPBC Act approval condition did not bring down the whole approval.

INTRODUCTION AND BACKGROUND

The Full Court of the Federal Court (Full Court) recently handed down its decision in Buzzacott v Minister for Sustainability, Environment, Water, Population and Communities [2013] FCAFC 111 (Buzzacott) an administrative law appeal brought by Mr Buzzacott, an Aboriginal elder, against the April 2012 decision of Justice Besanko in Buzzacott v Minister for Sustainability, Environment, Water, Population and Communities (No 2) [2012] FCA 403. Justice Besanko had dismissed the initial appeal brought by Mr Buzzacott to quash the decision of the Federal Minister for Sustainability, Environment, Water, Population and Communities (Minister) approving, with conditions (Approval), BHP Billiton Olympic Dam Corporation Pty Ltd's (BHPB's) proposal to expand the existing Olympic Dam copper, uranium, gold and silver mine and processing plant, including all associated