WHO SHOULD READ THIS

  • All resources proponents, operators, investors, planners and consultants.

WHAT DO YOU NEED TO KNOW

  • The new progressive rehabilitation and mine closure regime commences today, on 1 November 2019, which affects the obligations of EA holders in Queensland to progressively plan for rehabilitation and mine closure, and meet those binding commitments.

WHAT YOU NEED TO DO

  • Identify when your site may be transitioned into the new regime.
  • Seek advice regarding your likely obligations, particularly having to existing mine planning documents.
  • Commence mine planning, engagement with consultants and with the regulators accordingly.

Existing environmental authority (EA) holders will start being transitioned into the new progressive rehabilitation regime from today, 1 November 2019, under the Mineral and Energy Resources (Financial Provisioning) Act 2018 (Qld) (MERFP Act) amendments.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from