Contractors May Need To Formally "Invoice" All Costs To Protect Interest Rates

In any construction project, when changes, modifications, alterations, or deviations are ordered, the risk for delays and extra costs is high. Contractors obligated to implement...

United StatesReal Estate and Construction

In any construction project, when changes, modifications, alterations, or deviations are ordered, the risk for delays and extra costs is high. Contractors obligated to implement and supply those changes are vulnerable, incurring costs that may not be paid timely or even paid at all. As a result, contractors often include "extra cost" and "interest rate" provisions in their contract to cover ordered changes and untimely paid invoices. However, despite performing the extra work—and despite late payment, a contractor may not be entitled to a contracted interest rate if the contractor does not properly submit a formal "invoice."

In the recent unpublished opinion Cascade Concrete Industries, Inc. v. Central Washington Asphalt, Inc., et al. (Case No. 40429-3-III), dated December 23, 2025, the Division Three Washington State Court of Appeals reminds all contractors how important it is to know and follow every word of your written contract—especially when changes are

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.