On 07 July 2020, the Ministry of Industry and Trade ("MOIT") issued Circular No. 16/2020/TT-BCT to amend and supplement certain provisions of Circular No. 44/2-15/TT-BCT

VietnamFinance and Banking

On 07 July 2020, the Ministry of Industry and Trade ("MOIT") issued Circular No. 16/2020/TT-BCT to amend and supplement certain provisions of Circular No. 44/2-15/TT-BCT dated 09 December 2015 of the MOIT Minister on project development, avoided cost tariff and standardized power purchase agreement for biomass power projects.

In particular, this new Circular provides that investors be only allowed to build on-grid biomass power investment projects, which have been included in the approved Power Development Plan or Provincial Power Development Plan.

In addition, feed-in-tariff for on-grid biomass power projects will follow Decision No. 08/2020/QD-TTg dated 05 march 2020, which increases the feed-in tariff for biomass co-generation heat power to 7.03 US cents per kilowatt hour (up from 5.8 US cents), and for other types of biomass projects to 8.47 US cents per kWh (up from 7.3 to 7.5 US cents depending on location).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

Disclaimer: This Alert has been prepared and published for informational purposes only and is not offered, nor should be construed, as legal advice. For more information, please see the firm's full disclaimer.

See more popular content from