Following the issuance of the Power Development Plan VIII under Decision No. 500/QD-TTg of the Prime Minister dated 15 May 2023 (PDP 8), on 7 June 2023, the People's Committee of Ca Mau Province...

VietnamEnergy and Natural Resources

Following the issuance of the Power Development Plan VIII under Decision No. 500/QD-TTg of the Prime Minister dated 15 May 2023 (PDP 8), on 7 June 2023, the People's Committee of Ca Mau Province (Ca Mau PC) issues Official Letter No. 4201/UBND-KT on the proposal to recognize the list of projects under PDP 8 (Official Letter 4201). The submission of Official Letter 4201 is due to the fact that, since the PDP 8 has not specified the renewable projects in the power planning, it is the provincial authorities' obligation to submit the list of potential renewable projects for the evaluation of the Ministry of Industry and Trade (MOIT) and the Prime Minister.

According to Official Letter 4201, the Ca Mau PC expressly proposes to prioritize the development of renewable sources of energy, especially offshore wind and LNG. As for the detailed renewable projects, Ca Mau PC proposes the total capacity for renewable energy of 13,582 MW, including 34 wind power projects (13,068

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

Disclaimer: This Alert has been prepared and published for informational purposes only and is not offered, nor should be construed, as legal advice. For more information, please see the firm's full disclaimer.

See more popular content from