On 25 June 2020, under Dispatch No.795/TTg-CN, the Prime
Minister announced list of wind power projects and grids to be
considered for inclusion in the national electricity development
planning. The list entails name, location, capacity, connection
plans and conditions to release capacity of each project.
The list focuses on 5 regions, of which the Southwest area
(including Bac Lieu, Ben Tre, Soc Trang provinces) has the highest
number of projects – 3166.8 MW waiting to be included in the
power master plan. Follow up is the Central Highlands (Gia Lai, Dak
Lak, Dac Nong provinces) with 2432 MW. Next is the North Central
region with 941.2 MW of wind projects concentrated mostly in Quang
Tri province waiting to be included in the national power
development planning.