Vietnam's Prime Minister Decision 31/2014/QÐ-TTg on
solid waste-to-energy projects becomes effective as of today (20
June 2014). Article 14 of the Decision provides a ground-breaking
feed-in tariff for power suppliers of up to "VND 2,114/kWh
(equivalent to 10.05 US cents/kWh)". This is
more than 25 percent higher than the 7.8 cent applicable to wind
power projects in Article 14 of Decision 37/2011/QÐ-TTg from
2011. 10 cent per kWh was long considered the minimum threshold for
investments into renewable energy projects.
Although, Decision 31 is effective now, the Ministry of Industry
and Trade (MOIT) still has to issue the required "Standardized
Power Purchasing Agreement" (SPPA). MOIT has not responded to
inquiries on when it would release such SPPA. Pending issuance of
the new SPPA specifically for energy-from-waste projects, investors
may look to the existing SPPAs for small renewable power plants as
well as wind power as a basis.