The Impact Of Corrective Work On Performance Bond Deadlines: A Case Study

Duane Morris LLP
Duane Morris LLP
Contributor
Explore more from Duane Morris LLP

The recent decision in BCC Housing Development Corp. v. LPCiminelli, Inc., entered on February 27, 2025, by the New York Supreme Court...

United StatesReal Estate and Construction

The recent decision in BCC Housing Development Corp. v. LPCiminelli, Inc., entered on February 27, 2025, by the New York Supreme Court, Appellate Division, Third Department, addresses the enforcement of contractual time limits in performance bonds and clarifies when a contractor's work is considered complete under a construction contract.

BCC Housing Development Corp. ("BCC") engaged LPCiminelli, Inc. ("LPCiminelli") to construct student housing for SUNY Broome Community College. As required by the contract, LPCiminelli executed a performance bond issued by defendant Liberty Mutual Insurance Company, as surety. The bond required that any action on the bond be commenced within two years after the contractor stopped work. Substantial Completion of the project occurred in August 2014. The building housed students starting in the 2014–2015 academic year. The Final Payment was made in June 2015. However, construction defects required LPCiminelli to perform corrective

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

Disclaimer: This Alert has been prepared and published for informational purposes only and is not offered, nor should be construed, as legal advice. For more information, please see the firm's full disclaimer.

See more popular content from