IRS Broadens Prior "Beginning Of Construction" Guidance

Last week the Internal Revenue Service (IRS) issued Notice 2017-04, which updates its prior guidance concerning the beginning of construction deadline for the PTC and ITC...

United StatesReal Estate and Construction

Last week the Internal Revenue Service (IRS) issued Notice 2017-04, which updates its prior guidance concerning the beginning of construction deadline for the PTC and ITC, which applies to wind and other facilities eligible for the PTC or the ITC in lieu of the PTC. Notice 2017-04 clarifies, modifies, and extends prior guidance in several respects:

  • Continuity Safe Harbor – Deadline. Prior guidance provided that a facility would satisfy the Continuity Safe Harbor if a taxpayer places the facility in service by the later of (i) the calendar year that is no more than four calendar years after the calendar year during which construction of the facility began and (ii) December 31, 2016. Notice 2017-04 expands the Continuity Safe Harbor by extending the December 31, 2016, deadline to December 31, 2018. This change provides helpful relief for those projects that may have begun construction several years ago under either the Physical Work Test or the Five Percent Safe

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from