Contractor's Repeated Material Breach Excuses Subcontractor From Further Performance

This case involved a school construction project in which U.W. Marx, Inc., the general contractor, subcontracted with Koko Contracting, Inc. for roofing work.

United StatesReal Estate and Construction

The Appellate Division of the Supreme Court of New York in U.W. Marx, Inc. v. Koko Contracting, Inc. affirmed judgment in favor of a subcontractor, holding that the general contractor's failure to make three successive progress payments to the subcontractor resulted in a material breach, thereby relieving the subcontractor from performing its remaining work under the contract.

This case involved a school construction project in which U.W. Marx, Inc., the general contractor, subcontracted with Koko Contracting, Inc. for roofing work. Despite repeated demands for payment, Marx failed to pay Koko for three months of work. As a result, Koko stopped performance and left the site. Koko's abrupt work stoppage potentially violated a subcontract provision requiring it to give seven days notice of any suspension of work based on nonpayment. The relevant subcontract provision stated:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from