Quantum meruit is a legal theory that allows a
party to recover compensation if they provided services to another
with the expectation of payment, but without an explicit agreement
as to an amount.1 Quantum
meruit claims are frequently alleged in construction
cases, with a contractor claiming they provided construction
services to a project owner, who would be unjustly enriched if not
required to pay for them.
In Seabold Construction Co., Inc. v. KOZ 2211 SW
4th Ave., LLC,2 the Oregon
Court of Appeals reaffirmed the principle that a quantum
meruit claim cannot be used to save a contractor just
because the parties' written contract does not provide all
desired relief. In Seabold, the contractor claimed
that the owner caused delays in the project, which caused the
contractor to "incur additional costs, expenses, and lost
profits," for which it should be
compensated.3 But the contractor had a problem: the
parties' written contract included an express provision