During a construction project, it is not uncommon for disputes
to arise between a general contractor and a subcontractor.
Frequently, these disputes involve claims for extra work and delay
damages that can be attributed to the owner of the project due to
deficient design or unforeseen conditions. When these occasions
arise, the parties can often resolve these claims without the need
for litigation or arbitration by entering into a "liquidating
agreement."
What is a Liquidating Agreement?
Because there is no direct contractual relationship between a
subcontractor and an owner, there does not exist a legal basis for
a subcontractor to assert a breach of contract claim against a
project owner. In legal parlance, this is known as "lack of
contractual privity." A liquidating agreement bridges this
contractual gap and allows a subcontractor to pass its claim
against the owner through the general contractor. Essentially, with
a liquidating agreement, the general