On August 3, 2026, Governor Greg Abbott issued a directive to the Public Utility Commission of Texas (PUC) and the Electric Reliability Council of Texas (ERCOT) mandating a “comprehensive verification and audit” of all data center projects currently advancing through the ERCOT interconnection process. This action effectively imposes an immediate pause on approvals, requiring that this audit be completed before any additional data center projects are permitted to move forward.
The Governor’s directive is a response to unprecedented load growth—with data centers representing approximately 90 percent of the 474 gigawatts of new power requests—and aims to protect grid reliability, water resources, and community interests. Projects that fail to comply with the audit’s transparency requirements or state law will be denied connection to the primary Texas grid.