On January 17, 2019, the United States Court of Appeals for the
Fifth Circuit (the "FifthCircuit") issued a decision in
In re Ultra Petroleum Corp. that could have significant
implications for creditors seeking payment of contractual
make-whole amounts and post-petition interest from chapter 11
debtors.1
The Fifth Circuit's substantive legal holding is relatively
narrow—a creditor is not "impaired" under a plan
for purposes of section 1124 of the Bankruptcy Code if the
creditor's claim is altered solely by the Bankruptcy Code's
disallowance provisions, rather than the plan itself. This holding
follows the reasoning articulated by the Third Circuit in In re
PPI Enterprises (US), Inc., 324 F.3d 197, 201-02 (3d Cir.
2003). In PPI Enterprises, the Third Circuit held that a
landlord who is paid its full rejection damage claim, as capped by
section 502(b)(6) of the Bankruptcy Code, is unimpaired for plan
confirmation purposes, even though the capped claim is less