The Court of Federal Claims signaled recently, in a split with Government Accountability Office (GAO) case law, that the court would entertain a bid protest brought by an Indefinite Delivery Indefinite Quantity...

United StatesGovernment, Public Sector

The Court of Federal Claims signaled recently, in a split with Government Accountability Office (GAO) case law, that the court would entertain a bid protest brought by an Indefinite Delivery Indefinite Quantity (IDIQ) contract awardee challenging an agency's decision to award additional contracts under the same solicitation.

In Nat'l Air Cargo Grp., Inc. v. United States, No. 16-362C, Judge Lettow held that increased competition for task orders under an IDIQ contract could constitute a "non-trivial competitive injury," creating standing in court to challenge an award to another contractor where the Government allegedly failed to follow the terms of a solicitation or applicable procurement law. This directly contradicts GAO's ruling on the same issue and facts in Nat'l Air Cargo Grp., Inc., B-411830.2, Mar. 9, 2016, 2016 CPD ¶ 85, in which GAO stated that, "where a solicitation contemplates multiple awards, an existing contract awardee is not an interested party