ARTICLE · 20 MAY 2020

Sudden Loss Of Nationwide Permit 12 Threatens Future Of Development Projects; Will Overwhelm The Corps Of Engineers

A recent federal court ruling on the use of Nationwide Permit 12, in connection with the Keystone XL pipeline project in Montana, threatens the feasibility of current and future development projects nationwide ...

United StatesEnvironment

A recent federal court ruling on the use of Nationwide Permit 12 (NWP 12), in connection with the Keystone XL pipeline project in Montana, threatens the feasibility of current and future development projects nationwide as the U.S. Corps of Engineers (Corps) braces for an increase in individual Clean Water Act (CWA) permit review. The Montana court vacated NWP 12 and two days later, the Corps issued guidance to each of its regional regulatory offices to suspend all NWP 12 verifications until further notice.

The ruling, issued in Northern Plains Resource Council v. U.S. Army Corps of Engineers, No. 4:19-cv-00044-BMM (D. Mont.), held the Corps failed to consult with the U.S. Fish and Wildlife Service and the National Marine Fisheries Service (the Services) when it reissued a new set of Nationwide Permits in 2017. Section 7(a)(2) of the Endangered Species Act (ESA) requires agencies to consult with the Services when federal action "may affect" an endangered or

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from