ARTICLE · 06 NOVEMBER 2018

Southern District Of New York Confirms Arbitration Award Despite Allegation Of Undisclosed Real Party In Interest

After Hurricane Sandy hit the east coast in 2012, the Army Corps of Engineers contracted with Environmental Chemical Corp. (ECC) to conduct clean up on Fire Island, New York.

United StatesEnvironment

After Hurricane Sandy hit the east coast in 2012, the Army Corps of Engineers contracted with Environmental Chemical Corp. (ECC) to conduct clean up on Fire Island, New York. ECC subcontracted most of the work to Coastal Environmental Group, Inc. (Coastal). Both entities incurred unexpected costs, which ECC blamed on Coastal and Coastal blamed on factors outside of its control. ECC then refused to pay Coastal a portion of the money it was otherwise due under the contract, and Coastal commenced an arbitration that ended with an award in Coastal's favor.

ECC moved to vacate the award, focusing on two main issues: (1) Coastal's failure to disclose the interest of its creditor Signature Bank in the matter; and (2) the arbitrator's decision that ECC was estopped from challenging certain calculations of costs that Coastal had provided during the litigation because ECC has used those same calculations in submissions to the Army Corps of Engineers.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from